Contract award · N6274223F4007
FY23 MCON PROJECT P-209, DRY DOCK 3 REPLACEMENT, JOINT BASE PEARL HARBOR HICKAM, HAWAII
Awarded to DRAGADOS/HAWAIIAN DREDGING/ORION JV · CAGE 94AZ0
Latest reported total obligated
$3.3B
Net observed obligations
$3.1B
Observed contract actions
41
Observed period
FY2023–FY2026
Reported totals are cumulative values from the latest available award record. Observed obligations and actions reflect Mimir's FY2019 onward transaction window and may omit earlier activity.
Award parties and scope
ContractorDRAGADOS/HAWAIIAN DREDGING/ORION JV
CAGE94AZ0
Recipient UEIE8AXVANBZBD4
Ultimate parentDRAGADOS/HAWAIIAN DREDGING/ORION JV
Parent UEIE8AXVANBZBD4
CustomerDepartment of the Navy
Performance locationHONOLULU, HAWAII, UNITED STATES
Procurement details
Reported performance startMar 31, 2023
First observed actionMar 10, 2023
Latest observed actionJun 17, 2026
Reported current value$3.5B
Reported potential value$3.5B
PSCY1ED
NAICS237990 · Other Heavy and Civil Engineering Construction
CompetitionFULL AND OPEN COMPETITION
PricingFIXED PRICE AWARD FEE
SolicitationN6274222R1315
Annual observed obligations
FY2023
$463M
FY2024
$790.4M
FY2025
$1.5B
FY2026
$353.4M
Continue exploring
Ask Mimir about N6274223F4007
Continue with this contract award already in context.
ContinueExplore the full award in Mimir
Open the complete action history and connected analysis in the platform.